MISO Responds to Jefferson Parish Council Over May 25th Power Outage

by

in
MISO has addressed a letter from the Jefferson Parish Council concerning the May 25th power outage that impacted over 100,000 residents in areas like Mid-City, Lakeview, Metairie, and Terrytown. The outage resulted from a load shed event, a measure considered a last resort by MISO operators who attempted alternative solutions beforehand. The load shed was deemed necessary to avert more extensive damage and further power disruptions.

The incident stemmed from a combination of planned and unplanned generator outages. MISO provided a map illustrating the locations of generator failures and previously damaged generators that contributed to the emergency.

A detailed timeline revealed the rapid sequence of events, with the emergency declared at 4 p.m. and the load shed directive issued just two minutes later at 4:02 p.m. Contact with Entergy and Cleco to initiate the load shedding process occurred at 4:21 p.m. and 4:30 p.m., respectively.

MISO acknowledged in its response that the notification provided to power companies was insufficient and has pledged to refine communication procedures to enhance future responses.

MISO Responds to Jefferson Parish Council Over May 25th Power Outage

For more information visit: https://www.wdsu.com/article/jefferson-parish-council-power-outage-miso-letter-response/65115756