The incident stemmed from a combination of planned and unplanned generator outages. MISO provided a map illustrating the locations of generator failures and previously damaged generators that contributed to the emergency.
A detailed timeline revealed the rapid sequence of events, with the emergency declared at 4 p.m. and the load shed directive issued just two minutes later at 4:02 p.m. Contact with Entergy and Cleco to initiate the load shedding process occurred at 4:21 p.m. and 4:30 p.m., respectively.
MISO acknowledged in its response that the notification provided to power companies was insufficient and has pledged to refine communication procedures to enhance future responses.